Dept. of Trans. PROGRESS Serial No. Contract No. 23-261-09-25 04-0K1204 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 17% Location: Federal Project: 04-VAR-580 HSNH-000C(543) Progress payment No. 004 Payment period ending: 09-20-23 PERRY ELECTRIC INCORPORATED 130 MURWOOD CT WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 454,109.23 280,275.98 2. a. Extra Work 27,874.74 27,874.74 b. Adustment Comp. 3. Materials on Hand 128,602.97 -11,197.03 4. Earned Subject to Retention 610,586.94 296,953.69 5. Mobilization 207,500.00 0.00 6. Total Work Completed 689,483.97 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 818,086.94 296,953.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 296,953.69