Dept. of Trans. PROGRESS Serial No. Contract No. 25-258-17-06 04-0K1204 PROGRESS PAYMENT VOUCHER %complete: %time: 97% 88% Location: Federal Project: 04-VAR-580 HSNH-000C(543) Progress payment No. 028 Payment period ending: 09-20-25 PERRY ELECTRIC INCORPORATED 130 MURWOOD CT WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,980,936.31 490,079.19 2. a. Extra Work 1,610,417.18 242,154.85 b. Adustment Comp. -481,335.21 -481,335.21 3. Materials on Hand 0.00 -108,417.64 4. Earned Subject to Retention 8,110,018.28 142,481.19 5. Mobilization 415,000.00 0.00 6. Total Work Completed 8,525,018.28 7. Deductions -22,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,502,518.28 142,481.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 142,481.19