Dept. of Trans. PROGRESS Serial No. Contract No. 17-268-13-59 04-0K1504 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 30% Location: Federal Project: 04-SON-12-R15.6/R15.6 NONE 04-SON-101-20.5/22.5 04-SON-116-R5.7/R5.7 Progress payment No. 001 Payment period ending: 09-20-17 PETERSON - CHASE GENERAL ENGINEERING CONSTRUCTION, INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 106,736.90 106,736.90 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 106,736.90 106,736.90 5. Mobilization 37,050.00 37,050.00 6. Total Work Completed 143,786.90 7. Deductions -1,826.59 -1,826.59 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 141,960.31 141,960.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 141,960.31