Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 18-079-08-19 04-0K1504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SON-12-R15.6/R15.6 NONE 04-SON-101-20.5/22.5 04-SON-116-R5.7/R5.7 Progress payment No. 006 Payment period ending: 12-07-17 PETERSON - CHASE GENERAL ENGINEERING CONSTRUCTION, INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 360,717.06 460.80 2. a. Extra Work 34,542.09 34,542.09 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 395,259.15 35,002.89 5. Mobilization 39,000.00 0.00 6. Total Work Completed 434,259.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 434,259.15 35,002.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,002.89