Dept. of Trans. PROGRESS Serial No. Contract No. 25-167-15-17 04-0K1604 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 79% Location: Federal Project: 04-ALA-80-R7.6/8.0 SIMG-801(998) 04-CC-80-0.0/13.5 Progress payment No. 024 Payment period ending: 06-20-25 BAY CITIES PAVING& GRADING INC PO BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,562,212.60 5,624,983.23 2. a. Extra Work 1,097,798.51 490,489.20 b. Adustment Comp. 3. Materials on Hand 2,689,409.56 77,336.53 4. Earned Subject to Retention 35,349,420.67 6,192,808.96 5. Mobilization 5,328,900.00 0.00 6. Total Work Completed 37,988,911.11 7. Deductions -56,460.00 -56,460.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,621,860.67 6,136,348.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,136,348.96