Dept. of Trans. PROGRESS Serial No. Contract No. 23-166-10-42 04-0K2404 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 21% Location: Federal Project: 04-SCL-237-7.1/8.0 ACNH-P237(14) Progress payment No. 002 Payment period ending: 06-20-23 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 459,223.40 215,044.70 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 459,223.40 215,044.70 5. Mobilization 273,750.00 91,250.00 6. Total Work Completed 732,973.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 732,973.40 306,294.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 306,294.70