Dept. of Trans. PROGRESS Serial No. Contract No. 17-262-11-25 04-0K2904 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 46% Location: Federal Project: 04-ALA-680-0.0/100.0 NONE 04-ALA-880-0.0/100.0 04-ALA-84-6.9 Progress payment No. 003 Payment period ending: 09-20-17 TPA CONSTRUCTION INC 2406 CLUBHOUSE DRIVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,734.00 7,560.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 21,734.00 7,560.00 5. Mobilization 6. Total Work Completed 21,734.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,734.00 7,560.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,560.00