Dept. of Trans. PROGRESS Serial No. Contract No. 18-081-11-19 04-0K2904 PROGRESS PAYMENT VOUCHER %complete: %time: 58% 73% Location: Federal Project: 04-ALA-680-0.0/100.0 NONE 04-ALA-880-0.0/100.0 04-ALA-84-6.9 Progress payment No. 008 Payment period ending: 03-20-18 TPA CONSTRUCTION INC 2406 CLUBHOUSE DRIVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 324,361.22 0.00 2. a. Extra Work 65,300.00 65,300.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 389,661.22 65,300.00 5. Mobilization 50,000.00 2,500.00 6. Total Work Completed 439,661.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 439,661.22 67,800.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 67,800.00