Dept. of Trans. PROGRESS Serial No. Contract No. 16-008-11-07 04-0K3104 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 37% Location: Federal Project: 04-ALA-580-0.0 NONE Progress payment No. 002 Payment period ending: 01-08-16 SUAREZ & MUNOZ CONSTRUCTION INC . . 20975 CABOT BLVD HAYWARD, CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 254,623.39 210,904.72 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 254,623.39 210,904.72 5. Mobilization 6. Total Work Completed 254,623.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 254,623.39 210,904.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 210,904.72