Dept. of Trans. PROGRESS Serial No. Contract No. 16-021-08-58 04-0K3104 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 57% Location: Federal Project: 04-ALA-580-0.0 NONE Progress payment No. 003 Payment period ending: 01-20-16 SUAREZ & MUNOZ CONSTRUCTION INC . . 20975 CABOT BLVD HAYWARD, CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 543,476.13 288,852.74 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 543,476.13 288,852.74 5. Mobilization 6. Total Work Completed 543,476.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 543,476.13 288,852.74 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 288,852.74