Dept. of Trans. PROGRESS Serial No. Contract No. 17-296-12-01 04-0K4504 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 40% Location: Federal Project: 04-SOL-37-R9.9/R9.9 NONE 04-SOL-80-2.2/42.3 04-SOL-680-12.6/12.6 Progress payment No. 002 Payment period ending: 10-20-17 ETIC 2285 MORELLO AVE PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 124,457.68 45,032.66 2. a. Extra Work 439.49 439.49 b. Adustment Comp. 20,232.50 20,232.50 3. Materials on Hand 4. Earned Subject to Retention 145,129.67 65,704.65 5. Mobilization 42,180.00 0.00 6. Total Work Completed 187,309.67 7. Deductions -10,180.08 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 177,129.59 65,704.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 65,704.65