Dept. of Trans. PROGRESS Serial No. Contract No. 17-325-10-12 04-0K4504 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 56% Location: Federal Project: 04-SOL-37-R9.9/R9.9 NONE 04-SOL-80-2.2/42.3 04-SOL-680-12.6/12.6 Progress payment No. 003 Payment period ending: 11-20-17 ETIC 2285 MORELLO AVE PLEASANT HILL CA 94523 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 159,183.29 34,725.61 2. a. Extra Work 22,779.73 22,340.24 b. Adustment Comp. 20,232.50 0.00 3. Materials on Hand 4. Earned Subject to Retention 202,195.52 57,065.85 5. Mobilization 44,400.00 2,220.00 6. Total Work Completed 246,595.52 7. Deductions -10,715.88 -535.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 235,879.64 58,750.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,750.05