Dept. of Trans. PROGRESS Serial No. Contract No. 24-079-10-44 04-0K5204 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 62% Location: Federal Project: 04-SON-12-11.0/T17.4 ACNH-P012(130) Progress payment No. 010 Payment period ending: 03-20-24 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,078,277.40 1,689,128.00 2. a. Extra Work 13,862.83 0.00 b. Adustment Comp. 3. Materials on Hand 320,789.30 9,812.30 4. Earned Subject to Retention 13,412,929.53 1,698,940.30 5. Mobilization 2,000,000.00 0.00 6. Total Work Completed 15,092,140.23 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,412,929.53 1,698,940.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,698,940.30