Dept. of Trans. PROGRESS Serial No. Contract No. 23-048-08-36 04-0K5704 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 0% Location: Federal Project: 04-SM-1-1.1/1.1 NONE Progress payment No. 001 Payment period ending: 02-20-23 GORDON N BALL INC 333 CAMILLE AVE ALAMO CA 94507 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 186,413.00 186,413.00 4. Earned Subject to Retention 186,413.00 186,413.00 5. Mobilization 77,900.00 77,900.00 6. Total Work Completed 77,900.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 264,313.00 264,313.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 264,313.00