Dept. of Trans. PROGRESS Serial No. Contract No. 22-111-14-19 04-0K6504 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 41% Location: Federal Project: 04-ALA-580-R1.5 SNHG-000C(535) Progress payment No. 003 Payment period ending: 04-20-22 HOSELEY CORPORATION PO BOX 881386 SAN FRANCISCO CA 94188 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 280,402.00 73,539.47 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 242,509.31 0.00 4. Earned Subject to Retention 522,911.31 73,539.47 5. Mobilization 213,750.00 45,000.00 6. Total Work Completed 494,152.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 736,661.31 118,539.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,539.47