Dept. of Trans. PROGRESS Serial No. Contract No. 22-231-09-34 04-0K6704 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 54% Location: Federal Project: 04-SM-82-19.8/19.8 ACNH-P082(31) Progress payment No. 006 Payment period ending: 08-20-22 REDGWICK CONSTRUCTION CO. 21 HEGENBERGER CT OAKLAND CA 94621 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 828,243.60 112,392.40 2. a. Extra Work 12,796.90 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 841,040.50 112,392.40 5. Mobilization 60,562.50 0.00 6. Total Work Completed 901,603.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 901,603.00 112,392.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,392.40