Dept. of Trans. PROGRESS Serial No. Contract No. 24-325-12-59 04-0K7804 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 60% Location: Federal Project: 04-SM-84-21.5/25.7 ACNH-P084(59) Progress payment No. 009 Payment period ending: 11-20-24 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,809,286.04 1,519,489.10 2. a. Extra Work 507,225.56 72,272.03 b. Adustment Comp. 3. Materials on Hand 66,881.25 -114,352.40 4. Earned Subject to Retention 16,383,392.85 1,477,408.73 5. Mobilization 1,660,000.00 0.00 6. Total Work Completed 17,976,511.60 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,043,392.85 1,477,408.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,477,408.73