Dept. of Trans. PROGRESS Serial No. Contract No. 16-141-09-16 04-0K8704 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 75% Location: Federal Project: 04-CC-4-22.8/23.8 NONE Progress payment No. 002 Payment period ending: 05-20-16 SUAREZ & MUNOZ CONSTRUCTION INC 20975 CABOT BLVD HAYWARD CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 279,140.62 117,191.28 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 279,140.62 117,191.28 5. Mobilization 6. Total Work Completed 279,140.62 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -11,719.13 -11,719.13 c. Reduction after 95% Comp. 9. Total pay to Contractor 267,421.49 105,472.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 105,472.15