Dept. of Trans. PROGRESS Serial No. Contract No. 17-090-18-29 04-0K8704 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 100% Location: Federal Project: 04-CC-4-22.8/23.8 NONE Progress payment No. 009 Payment period ending: 03-20-17 SUAREZ & MUNOZ CONSTRUCTION INC 2490 AMERICAN AVENUE HAYWARD CA 94545 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 794,452.94 61,340.94 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 794,452.94 61,340.94 5. Mobilization 6. Total Work Completed 794,452.94 7. Deductions -15,450.25 -15,450.25 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 779,002.69 45,890.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 45,890.69