Dept. of Trans. PROGRESS Serial No. Contract No. 17-355-12-14 04-0K9704 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 64% Location: Federal Project: 04-SM-380-5.9/6.8 NONE 04-SM-101-R20.4/R21.0 Progress payment No. 002 Payment period ending: 12-20-17 O'GRADY PAVING INC 2513 WYANDOTTE ST MOUNTAIN VIEW CA 94043 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 954,844.00 549,649.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 954,844.00 549,649.00 5. Mobilization 45,000.00 2,250.00 6. Total Work Completed 999,844.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 999,844.00 551,899.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 551,899.00