Dept. of Trans. PROGRESS Serial No. Contract No. 18-019-14-08 04-0P1504 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 43% Location: Federal Project: 04-SM-92-0.9/0.9 NONE Progress payment No. 004 Payment period ending: 12-31-17 RGW CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 343,104.40 19,887.37 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 343,104.40 19,887.37 5. Mobilization 6. Total Work Completed 343,104.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 343,104.40 19,887.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 19,887.37