Dept. of Trans. PROGRESS Serial No. Contract No. 18-155-14-03 04-0P1504 PROGRESS PAYMENT VOUCHER %complete: %time: 47% 83% Location: Federal Project: 04-SM-92-0.9/0.9 NONE Progress payment No. 009 Payment period ending: 05-18-18 RGW CONSTRUCTION INC 6267 SOUTHFRONT RD LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 920,031.20 464,383.42 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 920,031.20 464,383.42 5. Mobilization 6. Total Work Completed 920,031.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 920,031.20 464,383.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 464,383.42