Dept. of Trans. PROGRESS Serial No. Contract No. 18-016-09-13 04-0P1804 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 100% Location: Federal Project: 04-SON-12-17.6/18.5 NONE Progress payment No. 002 Payment period ending: 01-12-18 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 389,083.45 61,213.06 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 389,083.45 61,213.06 5. Mobilization 6. Total Work Completed 389,083.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 389,083.45 61,213.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,213.06