Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-105-10-40 04-0P2804 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-SM-280-20.4/R20.4 NONE Progress payment No. 006 Payment period ending: 12-07-18 REDWOOD ENGINEERING CONSTRUCTION 416 D ST REDWOOD CITY CA 94063 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,075.00 6,075.00 2. a. Extra Work 828,978.22 104,988.37 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 835,053.22 111,063.37 5. Mobilization 6. Total Work Completed 835,053.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 835,053.22 111,063.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 111,063.37