Dept. of Trans. PROGRESS Serial No. Contract No. 19-354-12-52 04-0P3604 PROGRESS PAYMENT VOUCHER %complete: %time: 94% 100% Location: Federal Project: 04-CC-24-R0.0/R7.7 NONE 04-CC-242-R0.9/R0.9 04-CC-680-R1.1/24.0 Progress payment No. 004 Payment period ending: 12-20-19 MYERS & SONS CONSTRUCTION LLC 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 890,969.02 44,809.88 2. a. Extra Work 9,786.97 9,786.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 900,755.99 54,596.85 5. Mobilization 93,000.00 0.00 6. Total Work Completed 993,755.99 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 993,755.99 54,596.85 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 54,596.85