Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-207-10-10 04-0P6104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 04-CC-680-2.6/4.4 NONE Progress payment No. 008 Payment period ending: 05-07-19 BORTOLUSSI AND WATKIN INC 77 LARKSPUR ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 374,707.65 14,021.25 2. a. Extra Work 13,008.75 4,720.47 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 387,716.40 18,741.72 5. Mobilization 49,900.00 0.00 6. Total Work Completed 437,616.40 7. Deductions -15.00 -15.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 437,601.40 18,726.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,726.72