Dept. of Trans. PROGRESS Serial No. Contract No. 19-234-14-42 04-0P8004 PROGRESS PAYMENT VOUCHER %complete: %time: 29% 100% Location: Federal Project: 04-SM-380-T4.7/6.8 NONE Progress payment No. 003 Payment period ending: 08-20-19 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 614,823.00 450,746.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 614,823.00 450,746.00 5. Mobilization 6. Total Work Completed 614,823.00 7. Deductions -18,000.00 -18,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -45,074.60 -45,074.60 c. Reduction after 95% Comp. 9. Total pay to Contractor 551,748.40 387,671.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 387,671.40