Dept. of Trans. PROGRESS Serial No. Contract No. 25-107-10-47 04-0P9204 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 11% Location: Federal Project: 04-ALA-680-M6.3/R6.7 ACIM-6801(993) Progress payment No. 001 Payment period ending: 04-20-25 MYERS & SONS CONSTRUCTION LLC 45 MORRISON AVE SACRAMENTO CA 95838 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 317,429.69 317,429.69 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 317,429.69 317,429.69 5. Mobilization 362,500.00 362,500.00 6. Total Work Completed 679,929.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 679,929.69 679,929.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 679,929.69