Dept. of Trans. PROGRESS Serial No. Contract No. 25-325-14-14 04-0P9304 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 43% Location: Federal Project: 04-CC-80-7.6 BFIM-801(958) 04-CC-80-12.8 Progress payment No. 004 Payment period ending: 11-20-25 BUGLER CONSTRUCTION INC 4847 HOPYARD RD #4 #395 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,521,166.25 392,800.00 2. a. Extra Work 54,709.09 54,709.09 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,575,875.34 447,509.09 5. Mobilization 565,250.00 119,000.00 6. Total Work Completed 2,141,125.34 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,141,125.34 566,509.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 566,509.09