Dept. of Trans. PROGRESS Serial No. Contract No. 24-229-13-59 04-0Q0404 PROGRESS PAYMENT VOUCHER %complete: %time: 26% 45% Location: Federal Project: 04-SM-35-26.2/27.9 SNHG-P035(14) 04-SM-35-27.9 Progress payment No. 003 Payment period ending: 08-20-24 ST FRANCIS ELECTRIC LLC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 445,271.39 133,682.21 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 332,243.00 0.00 4. Earned Subject to Retention 777,514.39 133,682.21 5. Mobilization 237,500.00 0.00 6. Total Work Completed 682,771.39 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,015,014.39 133,682.21 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 133,682.21