Dept. of Trans. PROGRESS Serial No. Contract No. 25-259-13-56 04-0Q1004 PROGRESS PAYMENT VOUCHER %complete: %time: 74% 43% Location: Federal Project: 04-ALA-580-20.7/R30.8 ACIM-5801(984) Progress payment No. 009 Payment period ending: 09-20-25 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 32,024,171.45 4,533,868.80 2. a. Extra Work 1,063,785.70 2,825.00 b. Adustment Comp. 3. Materials on Hand 36,275.98 -13,161.04 4. Earned Subject to Retention 33,124,233.13 4,523,532.76 5. Mobilization 4,500,000.00 0.00 6. Total Work Completed 37,587,957.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,624,233.13 4,523,532.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,523,532.76