Dept. of Trans. PROGRESS Serial No. Contract No. 25-198-13-23 04-0Q2004 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 41% Location: Federal Project: 04-CC-4-12.4/25.0 ACNH-P004(164) Progress payment No. 003 Payment period ending: 07-20-25 GHILOTTI BROS INC 525 JACOBY ST SAN RAFAEL CA 94901 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 787,010.97 426,810.67 2. a. Extra Work 20,735.97 20,735.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 807,746.94 447,546.64 5. Mobilization 150,000.00 7,500.00 6. Total Work Completed 957,746.94 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 957,746.94 455,046.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 455,046.64