Dept. of Trans. PROGRESS Serial No. Contract No. 24-080-09-15 04-0Q30U4 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 24% Location: Federal Project: 04-ALA-680-R11.0/R21.9 ACIM-6801(990) 04-CC-680-R0.0/0.9 Progress payment No. 012 Payment period ending: 03-20-24 BAY CITIES PAVING& GRADING INC PO BOX 6227 CONCORD CA 945246227 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 48,953,117.17 8,313,913.89 2. a. Extra Work 2,001,427.54 1,276,020.55 b. Adustment Comp. 248,614.15 425,218.75 3. Materials on Hand 2,791,629.05 596,267.95 4. Earned Subject to Retention 53,994,787.91 10,611,421.14 5. Mobilization 16,503,357.27 0.00 6. Total Work Completed 67,706,516.13 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 70,498,145.18 10,611,421.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,611,421.14