Dept. of Trans. PROGRESS Serial No. Contract No. 22-354-16-47 04-0Q4504 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 24% Location: Federal Project: 04-ALA-92-6.5/6.5 NONE Progress payment No. 004 Payment period ending: 12-20-22 HOSELEY CORPORATION PO BOX 881386 SAN FRANCISCO CA 94188 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 559,171.68 17,906.88 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 559,171.68 17,906.88 5. Mobilization 6. Total Work Completed 559,171.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 559,171.68 17,906.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,906.88