Dept. of Trans. PROGRESS Serial No. Contract No. 24-164-14-49 04-0Q6104 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 18% Location: Federal Project: 04-SM-1-37.1/38.1 CNHG-P001(696) Progress payment No. 002 Payment period ending: 06-20-24 HOSELEY CORPORATION PO BOX 881386 SAN FRANCISCO CA 94188 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 194,346.50 184,904.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 194,346.50 184,904.00 5. Mobilization 111,750.00 111,750.00 6. Total Work Completed 306,096.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 306,096.50 296,654.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 296,654.00