Dept. of Trans. PROGRESS Serial No. Contract No. 26-198-11-59 04-0Q7904 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 8% Location: Federal Project: 04-NAP-121-13.4/20.7 ACST-S121(18) Progress payment No. 002 Payment period ending: 07-20-26 GORDON N BALL INC 1777 OAKLAND BLVD #300 WALNUT CREEK CA 94596 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 637,966.00 427,925.00 2. a. Extra Work 85,000.00 85,000.00 b. Adustment Comp. 3. Materials on Hand 0.00 -96,705.35 4. Earned Subject to Retention 722,966.00 416,219.65 5. Mobilization 142,500.00 0.00 6. Total Work Completed 865,466.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 865,466.00 416,219.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 416,219.65