Dept. of Trans. PROGRESS Serial No. Contract No. 25-107-08-46 04-0Q8204 PROGRESS PAYMENT VOUCHER %complete: %time: 18% 2% Location: Federal Project: 04-NAP-29-11.6/13.0 PTNH-P029(153) Progress payment No. 003 Payment period ending: 04-20-25 RANGER PIPELINES INC. PO BOX 24109 SAN FRANCISCO CA 94124 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 646,855.00 494,915.00 2. a. Extra Work 1,154,150.67 1,154,150.67 b. Adustment Comp. 584,986.90 584,986.90 3. Materials on Hand 224,376.75 224,376.75 4. Earned Subject to Retention 2,610,369.32 2,458,429.32 5. Mobilization 1,725,000.00 1,725,000.00 6. Total Work Completed 4,110,992.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,335,369.32 4,183,429.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,183,429.32