Dept. of Trans. PROGRESS Serial No. Contract No. 20-038-15-38 04-0Q8504 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 15% Location: Federal Project: 04-LAK-29-0.0 NONE Progress payment No. 002 Payment period ending: 12-15-19 THE PROFESSIONAL TREE CARE CO 2828 EIGHTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 429,794.20 215,963.78 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 429,794.20 215,963.78 5. Mobilization 6. Total Work Completed 429,794.20 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 429,794.20 215,963.78 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 215,963.78