Dept. of Trans. PROGRESS Serial No. Contract No. 06-020-07-36 04-0R5404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 9% 04-SF-280-R4.0/R7.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 01-20-06 GOLDEN STATE BRIDGE INC 901 HOWE ROAD MARTINEZ CA 94553 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 54,427.00 50,427.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 54,427.00 50,427.00 5. Mobilization 55,000.00 55,000.00 6. Total Work Completed 109,427.00 7. Deductions -1,177.75 -177.75 8. a.Contract Retentions -5,442.70 -5,042.70 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 102,806.55 100,206.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,206.55