Dept. of Trans. PROGRESS Serial No. Contract No. 04-202-10-41 04-0T0424 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 50% 60% 04-SON-37-6.0/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 07-20-04 TRI COUNTY INCORPORATED 2475 STOCKTON ST NAPA CA 94559 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 159,889.69 6,619.32 2.a. Extra Work 100,165.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 260,054.69 6,619.32 5. Mobilization 12,000.00 0.00 6. Total Work Completed 272,054.69 7. Deductions 8. a.Contract Retentions -13,002.73 -330.96 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 259,051.96 6,288.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,288.36