Dept. of Trans. PROGRESS Serial No. Contract No. 02-109-15-48 04-0T1024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 4% 04-SOL-12-19.0/19.1 Federal Project: NH-P012(88) Progress payment No. 01 Payment period ending: 04-19-02 PARNUM PAVING INC 1500 GROVE STREET HEALDSBURG CA 95448 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 67,221.53 67,221.53 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 67,221.53 67,221.53 5. Mobilization 50,000.00 50,000.00 6. Total Work Completed 117,221.53 7. Deductions 8. a.Contract Retentions -6,722.15 -6,722.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 110,499.38 110,499.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 110,499.38