Dept. of Trans. PROGRESS Serial No. Contract No. 02-291-12-16 04-0T1024 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 75% 38% 04-SOL-12-19.0/19.1 Federal Project: NH-P012(88) Progress payment No. 07 Payment period ending: 10-18-02 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE, CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 719,286.91 186,818.50 2.a. Extra Work 24,678.98 7,068.89 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 743,965.89 193,887.39 5. Mobilization 100,000.00 0.00 6. Total Work Completed 843,965.89 7. Deductions 8. a.Contract Retentions -37,198.29 -9,694.36 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 806,767.60 184,193.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 184,193.03