Dept. of Trans. PROGRESS Serial No. Contract No. 09-356-09-15 04-0T10U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 48% 42% 04-SOL-12-7.9/20.6 Federal Project: ACST-P012(100) P-P012(100) Progress payment No. 10 Payment period ending: 12-20-09 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,828,886.11 869,125.88 2.a. Extra Work 136,359.55 67,161.65 b. Adjustment Comp. 115,515.92 22,025.82 3. Materials on Hand 36,656.50 0.00 4. Earned Subject to Retention 8,117,418.08 958,313.35 5. Mobilization 1,923,208.50 0.00 6. Total Work Completed 10,003,970.08 7. Deductions -1,200.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 10,039,426.58 958,313.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 958,313.35