Dept. of Trans. SEMI-FINAL Serial No. Contract No. 12-024-10-29 04-0T10U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 04-SOL-12-7.9/20.6 Federal Project: ACST-P012(100) P-P012(100) Progress payment No. 31 Payment period ending: 07-01-11 R G W CONSTRUCTION INC P O BOX 2910 LIVERMORE CA 94551 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,155,701.22 3,880.85 2.a. Extra Work 986,284.73 14,841.38 b. Adjustment Comp. 2,000,981.60 437,297.17 3. Materials on Hand 4. Earned Subject to Retention 21,142,967.55 456,019.40 5. Mobilization 2,024,430.00 0.00 6. Total Work Completed 23,167,397.55 7. Deductions -1,200.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,166,197.55 456,019.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 456,019.40