Dept. of Trans. PROGRESS Serial No. Contract No. 04-168-10-28 04-0T1444 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 41% 04-SOL-37-9.3/10.5 Federal Project: 04-SOL-29-4.7/5.9 NH Progress payment No. 17 Payment period ending: 06-20-04 O C JONES AND SONS INC AND M C M CONSTRUCTION INC A JOINT VENTURE 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 02024 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,043,435.75 1,128,288.21 2.a. Extra Work 501,502.76 52,752.09 b. Adjustment Comp. -2,796.00 -4,420.00 3. Materials on Hand 861,680.85 -156,988.83 4. Earned Subject to Retention 17,403,823.36 1,019,631.47 5. Mobilization 3,500,000.00 175,000.00 6. Total Work Completed 20,042,142.51 7. Deductions -25,283.78 -163.80 8. a.Contract Retentions -870,191.17 -50,981.58 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,008,348.41 1,143,486.09 10. Reduction Amt to Escrow 11. Payment to Escrow 870,190.00 12. Net Pymt. this Estimate 1,143,486.09