Dept. of Trans. PROGRESS Serial No. Contract No. 04-236-06-41 04-0T1444 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 50% 04-SOL-37-9.3/10.5 Federal Project: 04-SOL-29-4.7/5.9 NH Progress payment No. 19 Payment period ending: 08-20-04 O C JONES AND SONS INC AND M C M CONSTRUCTION INC A JOINT VENTURE 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 02024 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,807,776.30 1,014,157.61 2.a. Extra Work 684,146.69 17,276.55 b. Adjustment Comp. -458.77 0.00 3. Materials on Hand 600,486.58 -188,933.44 4. Earned Subject to Retention 19,091,950.80 842,500.72 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 21,991,464.22 7. Deductions -35,283.78 0.00 8. a.Contract Retentions -954,597.54 -42,125.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 21,602,069.48 800,375.68 10. Reduction Amt to Escrow 11. Payment to Escrow 954,590.00 12. Net Pymt. this Estimate 800,375.68