Dept. of Trans. PROGRESS Serial No. Contract No. 04-294-10-21 04-0T1444 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 58% 04-SOL-37-9.3/10.5 Federal Project: 04-SOL-29-4.7/5.9 NH Progress payment No. 21 Payment period ending: 10-20-04 O C JONES AND SONS INC AND M C M CONSTRUCTION INC A JOINT VENTURE 1520 FOURTH STREET BERKELEY CA 94710 Escrow No. 02024 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,438,878.66 1,054,655.32 2.a. Extra Work 962,752.83 102,073.97 b. Adjustment Comp. 94,723.73 0.00 3. Materials on Hand 505,938.85 -34,311.99 4. Earned Subject to Retention 21,002,294.07 1,122,417.30 5. Mobilization 3,500,000.00 0.00 6. Total Work Completed 23,996,355.22 7. Deductions -42,183.78 -3,600.00 8. a.Contract Retentions -1,050,114.70 -56,120.86 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 23,409,995.59 1,062,696.44 10. Reduction Amt to Escrow 11. Payment to Escrow 1,050,110.00 12. Net Pymt. this Estimate 1,062,696.44