Dept. of Trans. PROGRESS Serial No. Contract No. 13-164-18-36 04-0T1454 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 85% 04-SOL-37-7.2/10.5 Federal Project: 04-SOL-29-4.7/5.9 NH Progress payment No. 39 Payment period ending: 06-20-13 PARKER LANDSCAPE DEVELOPMENT INC 6251 SKY CREEK DRIVE SUITE A SACRAMENTO CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 826,275.64 3,875.77 2.a. Extra Work 87,695.48 0.00 b. Adjustment Comp. -10,673.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 903,298.12 3,875.77 5. Mobilization 20,057.00 0.00 6. Total Work Completed 923,355.12 7. Deductions -1,937.88 -1,937.88 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 921,417.24 1,937.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,937.89