Dept. of Trans. PROGRESS Serial No. Contract No. 03-051-12-20 04-0T14C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 10% 04-SOL-37-7.2/7.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 02-20-03 BAUMAN LANDSCAPE INC 115 BROOKSIDE DRIVE RICHMOND CA 94801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 130,678.00 79,900.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 82,741.64 61,915.96 4. Earned Subject to Retention 213,419.64 141,815.96 5. Mobilization 27,491.00 1,374.55 6. Total Work Completed 158,169.00 7. Deductions 8. a.Contract Retentions -10,670.98 -5,059.72 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 230,239.66 138,130.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 138,130.79