Dept. of Trans. PROGRESS Serial No. Contract No. 03-079-12-29 04-0T14C4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 7% 04-SOL-37-7.2/7.2 Federal Project: NONE Progress payment No. 06 Payment period ending: 03-20-03 BAUMAN LANDSCAPE INC 115 BROOKSIDE DRIVE RICHMOND CA 94801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 166,686.70 36,008.70 2.a. Extra Work 127,901.42 127,901.42 b. Adjustment Comp. 3. Materials on Hand 0.00 -82,741.64 4. Earned Subject to Retention 294,588.12 81,168.48 5. Mobilization 27,491.00 0.00 6. Total Work Completed 322,079.12 7. Deductions 8. a.Contract Retentions -14,729.41 -4,058.43 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 307,349.71 77,110.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 77,110.05